{"id":8024,"date":"2016-01-05T09:02:47","date_gmt":"2016-01-05T17:02:47","guid":{"rendered":"http:\/\/spijue.wpengine.com\/news\/gastineau-demolition-takes-first-big-bite-next-week\/"},"modified":"2016-01-05T09:02:47","modified_gmt":"2016-01-05T17:02:47","slug":"gastineau-demolition-takes-first-big-bite-next-week","status":"publish","type":"post","link":"https:\/\/www.juneauempire.com\/news\/gastineau-demolition-takes-first-big-bite-next-week\/","title":{"rendered":"Gastineau demolition takes first big bite next week"},"content":{"rendered":"

Like a worm in an apple, a bottle of Pepto-Bismol, or the face-hugging alien in \u201cAlien,\u201d the contractors demolishing the Gastineau Apartments will do their work from the inside out.<\/p>\n

In a noon presentation Monday, City and Borough of Juneau Public Works director Rorie Watt explained the process that, starting about Jan. 12, will bring down the century-old fire-damaged apartment building on Franklin Street.<\/p>\n

Rather than a wrecking ball or dynamite, \u201cthere\u2019s going to be a high-reach excavator, and they\u2019re going to break the building apart, probably using a variety of tools attached to the excavator,\u201d Watt explained.<\/p>\n

In a series of slides, he showed how the excavator, working from the former site of Gunakadeit Park, will first tear down the corner of the building adjacent to the park and farthest from Franklin Street. With the corner removed, the excavator will gnaw into the building, removing internal floors and debris. The building\u2019s exterior walls, and in particular the walls facing Franklin Street and the building now occupied by the Rockwell, will be the last pieces demolished. At times, the process will leave the excavator working within the building\u2019s hollow shell.<\/p>\n

\u201cIt\u2019s going to be a very methodical demolition of the structure,\u201d Watt said. \u201cOf course, there are going to be a lot of dump trucks, there\u2019s going to be a lot of detail work.\u201d<\/p>\n

Work began in December to demolish the first of three buildings in the Gastineau Apartments complex, which remains owned by James and Kathleen Barrett. Sitka-based CBC Construction was hired by the city of Juneau to demolish the complex, which was damaged by a pair of fires and has been vacant and steadily deteriorating since 2012.<\/p>\n

The Barretts contested a city demolition order, but the Juneau Assembly ultimately voted to issue a contract for the complex\u2019s removal. On Nov. 10, the city issued a notice to proceed to CBC, which was awarded the demolition contract at a cost of $1.37 million. The city is expected to seek repayment from the Barretts.<\/p>\n

On Monday, Watt and project engineer Rich Ritter explained that the demolition of the first Gastineau building – the one closest to Franklin Street – will take about two to three weeks. <\/p>\n

\u201cWe expect that to come down pretty quickly and efficiently,\u201d Watt said as a grinning, mustachioed man in the last row of the meeting room raised his crossed fingers for luck.<\/p>\n

CBC Construction has already pumped the building\u2019s basement dry, installed security cameras and performed preliminary demolition work, including on the building\u2019s Franklin Street awning. That work stopped for the Christmas and New Year\u2019s Day holidays. <\/p>\n

Before full-scale demolition begins next week, CBC will string screens to catch any falling debris, construct additional fences to keep spectators away, and perform pre-demolition surveys of surrounding buildings to identify any damage that might occur during demolition.<\/p>\n

After the first building is demolished, work will begin on the other two buildings, which sit slightly uphill. A demolition plan for those buildings has not been finished, but CBC\u2019s contract calls for work to be complete by the end of April.<\/p>\n

After demolition, the site of the apartment complex will be covered in gravel and surrounded by a semi-permanent chain-link fence.<\/p>\n","protected":false},"excerpt":{"rendered":"

Like a worm in an apple, a bottle of Pepto-Bismol, or the face-hugging alien in \u201cAlien,\u201d the contractors demolishing the Gastineau Apartments will do their work from the inside out. In a noon presentation Monday, City and Borough of Juneau Public Works director Rorie Watt explained the process that, starting about Jan. 12, will bring […]<\/p>\n","protected":false},"author":426,"featured_media":0,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_stopmodifiedupdate":false,"_modified_date":"","wds_primary_category":4,"footnotes":""},"categories":[4],"tags":[75],"yst_prominent_words":[],"class_list":["post-8024","post","type-post","status-publish","format-standard","hentry","category-news","tag-local-news"],"_links":{"self":[{"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/posts\/8024","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/users\/426"}],"replies":[{"embeddable":true,"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/comments?post=8024"}],"version-history":[{"count":0,"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/posts\/8024\/revisions"}],"wp:attachment":[{"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/media?parent=8024"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/categories?post=8024"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/tags?post=8024"},{"taxonomy":"yst_prominent_words","embeddable":true,"href":"https:\/\/www.juneauempire.com\/wp-json\/wp\/v2\/yst_prominent_words?post=8024"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}