Gas pipeline negotiations continue

No major new developments as state-owned corporation provides update to Legislature

Correction: The proposed pipeline would be 807 miles, not 907 miles.

The multibillion-dollar trans-Alaska natural gas pipeline project is still advancing, state lawmakers were told in a Wednesday morning hearing.

At a regular quarterly update in Anchorage, executives from the Alaska Gasline Development Corporation told legislators they are working on contracts with potential gas customers in Asia.

The corporation has 15 “letters of interest” from customers, and it is trying to turn those into “definitive agreements,” AGDC President Keith Meyer told reporters before Wednesday’s hearing. Meyer was meeting with potential investors and did not participate in the hearing.

Sen. Cathy Giessel, R-Anchorage, and Rep. Geran Tarr, D-Anchorage, chaired Wednesday’s meeting, and each said they didn’t hear anything particularly groundbreaking from Wednesday’s presentation, which included information from AGDC as well as the Alaska Department of Revenue and the Alaska Department of Natural Resources.

According to the latest figures presented at Wednesday’s meeting, the AKLNG (Alaska Liquefied Natural Gas) project would spend $44 billion to construct a 807-mile pipeline bracketed by a pair of massive industrial plants. At the southern end, in the Kenai Peninsula community of Nikiski, would be a facility designed to export the gas onto tankers bound for ports in Asia.

The plan, which is being pushed by Gov. Bill Walker as a successor to efforts started by former governors Sarah Palin and Sean Parnell, is the latest iteration of ideas that have been on the table since the trans-Alaska Pipeline System began shipping crude oil 41 years ago.

The AGDC, a state-owned corporation, is in charge of developing the project. That includes negotiating contracts with gas providers (North Slope oil companies) and gas buyers (utilities in Asia). With those deals in hand, the state would be able to find investors to fund construction of the project. When the pipeline begins operation, the plan calls for those investors to be paid off over a period of 20-30 years, leaving the state with full ownership.

While a gas pipeline has been a political issue since the 1970s, Department of Revenue deputy commissioner Mike Barnhill told lawmakers, “We may be at that point where we seriously consider how we do this.”

AGDC representatives provided an update on the multi-year federal permitting process and said they have found an American supplier for the steel pipe that may be used in the project. That matters because recent tariffs imposed by President Donald Trump on imported steel pipe had threatened to increase the cost of the pipeline.

“That’s a very good positive,” AGDC vice president Frank Richards said of the American supplier, “because previously we didn’t see that there was 42-inch (pipe) being rolled in the United States.”

Lawmakers are keeping a close eye on the project because the state is likely to shoulder a one-quarter share of construction costs. At $44 billion, that would mean an $11 billion payment.

The Alaska Permanent Fund is not seriously considering an investment at present, lawmakers were told.

Sens. Click Bishop, R-Fairbanks, and Bert Stedman, R-Sitka, each said that it will be absolutely critical for the state to be accurate with its cost estimates. Construction of the trans-Alaska oil pipeline system was three times as expensive as forecast, and a state-owned gas pipeline cannot do that.

“I don’t mind betting the cow,” Stedman said. “There’s no way I’m betting the farm.”


• Contact reporter James Brooks at jbrooks@juneauempire.com or 523-2258.


More in Home

Two flags with pro-life themes, including the lower one added this week to one that’s been up for more than a year, fly along with the U.S. and Alaska state flags at the Governor’s House on Tuesday. (Mark Sabbatini / Juneau Empire)
Doublespeak: Dunleavy adds second flag proclaiming pro-life allegiance at Governor’s House

First flag that’s been up for more than a year joined by second, more declarative banner.

Juneau Assembly Member Maureen Hall (left) and Mayor Beth Weldon (center) talk to residents during a break in an Assembly meeting Monday, Feb. 3, 2025, about the establishment of a Local Improvement District that would require homeowners in the area to pay nearly $6,300 each for barriers to protect against glacial outburst floods. (Mark Sabbatini / Juneau Empire)
Flood district plan charging property owners nearly $6,300 each gets unanimous OK from Assembly

117 objections filed for 466 properties in Mendenhall Valley deemed vulnerable to glacial floods.

Students play trumpets at the first annual Jazz Fest in 2024. (Photo courtesy of Sandy Fortier)
Join the second annual Juneau Jazz Fest to beat the winter blues

Four-day music festival brings education of students and Southeast community together.

Frank Richards, president of the Alaska Gasline Development Corp., speaks at a Jan. 6, 2025, news conference held in Anchorage by Gov. Mike Dunleavy. Dunleavy and Randy Ruaro, executive director of the Alaska Industrial Development and Export Authority, are standing behind RIchards. (Yereth Rosen/Alaska Beacon)
For fourth consecutive year, gas pipeline boss is Alaska’s top-paid public executive

Sen. Bert Stedman, R-Sitka, had the highest compensation among state legislators after all got pay hike.

State Rep. Rebecca Himschoot (right), I-Sitka, answers a question from Rep. Jubilee Underwood (right), R-Wasilla, about a bill increasing per-pupil public school funding during a House Education Committee meeting on Monday. (Mark Sabbatini / Juneau Empire)
Legislators and governor form working group seeking quick education funding and policy package

Small bipartisan group plans to spend up to two weeks on plan as related bills are put on hold.

Juneau-Douglas High School: Yadaa.at Kalé Nordic Ski Team and community cross-country skiers start the Shaky Shakeout Invitational six-kilometer freestyle mass start race Saturday at Eaglecrest Ski Area. (Klas Stolpe / Juneau Empire)
Crimson Bears cross-country skiers in sync

JDHS Nordic Ski Team tunes up for state with practice race

Thunder Mountain Middle School eighth grader Carter Day of the Blue Barracuda Bombers attempts to pin classmate John Croasman of War Hawks White during the inaugural Thunder Mountain Mayhem Team Duels wrestling tournament Saturday at TMMS. (Klas Stolpe / Juneau Empire)
Inaugural Thunder Mountain Mayhem Tournament makes most of weather misfortune

More than 50 Falcons wrestlers compete amongst themselves after trip to Sitka tourney nixed.

The roundabout at the intersection of Mendenhall Loop Road and Stephen Richards Memorial Drive on Monday morning after it was reopened following a shooting between two men in vehicles shortly after midnight. (Laurie Craig / Juneau Empire)
Motorist fatally shoots driver he says was threatening him with a gun at Mendenhall Valley roundabout

Shooter released after initial JPD investigation; 16-year-old victim had pellet/BB-style CO2 rifle

University of Alaska President Pat Pitney gives the State of the University address in Juneau on Jan. 30, 2025. She highlighted the wide variety of educational and vocational programs as creating opportunities for students, and for industries to invest in workforce development and the future of Alaska’s economy. (Corinne Smith/Alaska Beacon)
University of Alaska president highlights impact on workforce, research and economy in address

Pat Pitney also warns “headwinds” are coming with federal executive orders and potential budget cuts.

Most Read