Electric official outlines $15 million upgrades for Sitka

SITKA — Officials with Sitka’s electric department have plans for $15.7 million in projects over the next decade to address weaknesses in the city’s electric system and avoid major power emergencies.

Electric utility director Bryan Bertacchi told the Assembly Tuesday that top priorities in the 10-year plan target the distribution system as well as transmission and generation issues, the Sitka Sentinel reported.

Bertacchi recommends installing a new $11 million substation in the Kramer Avenue area to support the one on Marine Street. He said statistics show the existing substation could break down in the next 15 years due to aging transformers. A new facility could ease the load on the feeder line and minimize the risk of outages caused by distribution problems.

“If we wanted to go that way we could go that way now,” Bertacchi said. “If we had an emergency, we could find a way to hook it up instead of rotating blackouts.”

Other priorities in the plan include replacement of the overhead transmission line from the Blue Lake power plant to Thimbleberry trailhead, which would cost $3.8 million. The line transfers power from both Green and Blue lakes to Sitka.

Bertacchi said other priorities include a new Jarvis Street oil containment system, which could cost up to $1 million, and an internal inspection of Green Lake for $400,000.

Bertacchi is also calling on the city to consider less urgent projects, like a $7 million overhaul of the Green Lake hydro and work on the Marine Street substation for $1 million.

Finance Director Jay Sweeney said the city electric fund does not have sufficient funds to pay for the $23.7 million needed to cover both top-tier and second-tier projects.

“The key point I want to make is that, as it exists right now, combining all available cash proceeds, there is not enough to pay for everything in the plan,” he said.

The electric fund has $15.3 million in available working capital, including $9.5 million in unspent bond proceeds.

Bertacchi suggested that the Assembly consider spending remaining bond proceeds on the most necessary projects, using the undesignated fund balance of $8.5 million and raising utility rates. Other options would include living with the risks of not making critical repairs, Bertacchi said.

More in News

(Juneau Empire file photo)
Aurora forecast through the week of Feb. 1

These forecasts are courtesy of the University of Alaska Fairbanks’ Geophysical Institute… Continue reading

A person is detained in Anchorage in recent days by officials from the FBI and U.S. Department of Homeland Security. (FBI Anchorage Field Office photo)
Trump’s immigration raids arrive in Alaska, while Coast Guard in state help deportations at southern US border

Anchorage arrests touted by FBI, DEA; Coast Guard plane from Kodiak part of “alien expulsion flight operations.”

Two flags with pro-life themes, including the lower one added this week to one that’s been up for more than a year, fly along with the U.S. and Alaska state flags at the Governor’s House on Tuesday. (Mark Sabbatini / Juneau Empire)
Doublespeak: Dunleavy adds second flag proclaiming pro-life allegiance at Governor’s House

First flag that’s been up for more than a year joined by second, more declarative banner.

Students play trumpets at the first annual Jazz Fest in 2024. (Photo courtesy of Sandy Fortier)
Join the second annual Juneau Jazz Fest to beat the winter blues

Four-day music festival brings education of students and Southeast community together.

Frank Richards, president of the Alaska Gasline Development Corp., speaks at a Jan. 6, 2025, news conference held in Anchorage by Gov. Mike Dunleavy. Dunleavy and Randy Ruaro, executive director of the Alaska Industrial Development and Export Authority, are standing behind RIchards. (Yereth Rosen/Alaska Beacon)
For fourth consecutive year, gas pipeline boss is Alaska’s top-paid public executive

Sen. Bert Stedman, R-Sitka, had the highest compensation among state legislators after all got pay hike.

Juneau Assembly Member Maureen Hall (left) and Mayor Beth Weldon (center) talk to residents during a break in an Assembly meeting Monday, Feb. 3, 2025, about the establishment of a Local Improvement District that would require homeowners in the area to pay nearly $6,300 each for barriers to protect against glacial outburst floods. (Mark Sabbatini / Juneau Empire)
Flood district plan charging property owners nearly $6,300 each gets unanimous OK from Assembly

117 objections filed for 466 properties in Mendenhall Valley deemed vulnerable to glacial floods.

(Michael Penn / Juneau Empire file photo)
Police calls for Sunday, Feb. 2, 2025

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Saturday, Feb. 1, 2025

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Friday, Jan. 31, 2025

This report contains public information from law enforcement and public safety agencies.

Most Read