State regulators to take closer look at AEL&P’s diesel power plans

The Regulatory Commission of Alaska will take a closer look at Alaska Electric Light & Power’s under-construction diesel power plant on Industrial Boulevard.

In an order published by the commission Wednesday, state regulators asked AEL&P for additional information about the need for the plant, and for studies analyzing what will happen to Juneau’s electric grid and the city as a whole when it is switched on.

The order has no effect on construction of the plant, which is still scheduled to begin operations in October, AEL&P vice president Debbie Driscoll said by phone.

The RCA’s request for more information was partially driven by a complaint from Danielle Redmond, a Juneau resident and passionate proponent of clean power. Redmond is coordinator of the Alaska Climate Action Network but filed the complaint as an ordinary resident, she said.

While AEL&P is promoting the new plant as a backup power source if hydroelectricity is unavailable, “it’s really hard to claim that when it’s 23 megawatts of power and especially hard to claim that when AEL&P says there isn’t a need for more electricity,” Redmond said by phone.

Redmond was referring to comments made by AEL&P to the Federal Energy Regulatory Commission about the Sweetheart Lake hydroelectric project, a 19-megawatt effort planned by Juneau Hydropower Inc., an organization unaffiliated with AEL&P.

In her complaint, she asked whether the company actually intends to use the plant as primary generation for the Greens Creek mine. AEL&P announced plans along those lines in February.

For its part, the company has maintained that it will use the new plant to supply Juneau’s needs in the event that Snettisham hydroelectric power is unavailable.

Driscoll said the new plant’s purpose is to meet the backup power needs of existing AEL&P customers. In the event of a hydropower-severing disaster on a cold day, the company does not have enough power to easily meet Juneau’s needs.

“This is a backup unit that would serve our existing customers if we’re cut off from our hydro sources,” Driscoll said.

She added that unfortunately, Juneau’s primary hydropower options are all south of the city, which makes hydropower backup options difficult to find.

In Wednesday’s filing, the RCA says “it is in the public interest for the (Attorney General) to participate in this proceeding as a party. The chairman therefore invites the AG to participate.”

Robert Pickett, chairman of the RCA’s board of commissioners said that invitation is common, but it’s not done on every case.

The RCA does not make go/no-go decisions on power projects in Alaska. Rather, it regulates the rates that utilities are permitted to charge customers.

In this case, AEL&P had asked RCA for permission to set a “depreciation rate” on the new power plant. “AELP requests that the proposed depreciation rate be approved for accounting purposes only. AELP is not seeking any change in electric rates at this time,” the company said in a July 20 filing.

The new power plant is sure to eventually result in higher electric rates, however.

“All of our infrastructure investments impact our rates down the road,” AEL&P President Tim McLeod told the Juneau Chamber of Commerce earlier this month. “There will be some inflation.”

The amount of that “inflation” will be determined by a future rate request from AEL&P to the RCA. The amount of that future rate request will be partially determined by the matter now under consideration.

Driscoll said the information requested by the RCA is unusual at this point in time, but because AEL&P was planning to request a rate increase later this year, it is happy to provide the information now.

AEL&P and the general public are allowed to comment on the matter before Aug. 18. Email rod.crum@alaska.gov and reference Docket U-16-067 in the headline of the email.

The RCA has scheduled a preliminary hearing on Aug. 19 to consider a timeline of decision. It expects to decide the matter by Jan. 16.

• Contact reporter James Brooks at 523-2258 or james.k.brooks@juneauempire.com.

 

More news:

 

More in News

(Juneau Empire file photo)
Aurora forecast through the week of Feb. 1

These forecasts are courtesy of the University of Alaska Fairbanks’ Geophysical Institute… Continue reading

A sign at the former Floyd Dryden Middle School on Monday, June 24, 2025, commemorates the school being in operation from 1973 to 2024. (Jasz Garrett / Juneau Empire file photo)
Assembly ponders Floyd Dryden for tribal youth programs, demolishing much of Marie Drake for parking

Tlingit and Haida wants to lease two-thirds of former middle school for childcare and tribal education.

A person is detained in Anchorage in recent days by officials from the FBI and U.S. Department of Homeland Security. (FBI Anchorage Field Office photo)
Trump’s immigration raids arrive in Alaska, while Coast Guard in state help deportations at southern US border

Anchorage arrests touted by FBI, DEA; Coast Guard plane from Kodiak part of “alien expulsion flight operations.”

Two flags with pro-life themes, including the lower one added this week to one that’s been up for more than a year, fly along with the U.S. and Alaska state flags at the Governor’s House on Tuesday. (Mark Sabbatini / Juneau Empire)
Doublespeak: Dunleavy adds second flag proclaiming pro-life allegiance at Governor’s House

First flag that’s been up for more than a year joined by second, more declarative banner.

Students play trumpets at the first annual Jazz Fest in 2024. (Photo courtesy of Sandy Fortier)
Join the second annual Juneau Jazz Fest to beat the winter blues

Four-day music festival brings education of students and Southeast community together.

Frank Richards, president of the Alaska Gasline Development Corp., speaks at a Jan. 6, 2025, news conference held in Anchorage by Gov. Mike Dunleavy. Dunleavy and Randy Ruaro, executive director of the Alaska Industrial Development and Export Authority, are standing behind RIchards. (Yereth Rosen/Alaska Beacon)
For fourth consecutive year, gas pipeline boss is Alaska’s top-paid public executive

Sen. Bert Stedman, R-Sitka, had the highest compensation among state legislators after all got pay hike.

Juneau Assembly Member Maureen Hall (left) and Mayor Beth Weldon (center) talk to residents during a break in an Assembly meeting Monday, Feb. 3, 2025, about the establishment of a Local Improvement District that would require homeowners in the area to pay nearly $6,300 each for barriers to protect against glacial outburst floods. (Mark Sabbatini / Juneau Empire)
Flood district plan charging property owners nearly $6,300 each gets unanimous OK from Assembly

117 objections filed for 466 properties in Mendenhall Valley deemed vulnerable to glacial floods.

(Michael Penn / Juneau Empire file photo)
Police calls for Sunday, Feb. 2, 2025

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Saturday, Feb. 1, 2025

This report contains public information from law enforcement and public safety agencies.

Most Read